Sprint Planning
Plan a sprint by estimating team capacity, selecting and sequencing stories, and identifying risks.
Context
You are helping plan a sprint for $ARGUMENTS.
If the user provides files (backlogs, velocity data, team rosters, or previous sprint reports), read them first.
Instructions
Estimate team capacity:
- Number of team members and their availability (PTO, meetings, on-call)
- Historical velocity (average story points per sprint from last 3 sprints)
- Capacity buffer: reserve 15-20% for unexpected work, bugs, and tech debt
- Calculate available capacity in story points or ideal hours
Review and select stories:
- Pull from the prioritized backlog (highest priority first)
- Verify each story meets the Definition of Ready (clear AC, estimated, no blockers)
- Flag stories that need refinement before committing
- Stop adding stories when capacity is reached
Map dependencies:
- Identify stories that depend on other stories or external teams
- Sequence dependent stories appropriately
- Flag external dependencies and owners
- Identify the critical path
Identify risks and mitigations:
- Stories with high uncertainty or complexity
- External dependencies that could slip
- Knowledge concentration (only one person can do it)
- Suggest mitigations for each risk
Create the sprint plan summary:
Sprint Goal: [One sentence describing what success looks like] Duration: [2 weeks / 1 week / etc.] Team Capacity: [X story points] Committed Stories: [Y story points across Z stories] Buffer: [remaining capacity] Stories: 1. [Story title] — [points] — [owner] — [dependencies] ... Risks: - [Risk] → [Mitigation]Define the sprint goal: A single, clear sentence that captures the sprint's primary value delivery.
Think step by step. Save as markdown.
Further Reading
| 1 | |
| 2 | name sprint-plan |
| 3 | description "Plan a sprint with capacity estimation, story selection, dependency mapping, and risk identification. Use when preparing for sprint planning, estimating team capacity, selecting stories, or balancing sprint scope against velocity." |
| 4 | |
| 5 | |
| 6 | ## Sprint Planning |
| 7 | |
| 8 | Plan a sprint by estimating team capacity, selecting and sequencing stories, and identifying risks. |
| 9 | |
| 10 | ### Context |
| 11 | |
| 12 | You are helping plan a sprint for **$ARGUMENTS**. |
| 13 | |
| 14 | If the user provides files (backlogs, velocity data, team rosters, or previous sprint reports), read them first. |
| 15 | |
| 16 | ### Instructions |
| 17 | |
| 18 | **Estimate team capacity**: |
| 19 | Number of team members and their availability (PTO, meetings, on-call) |
| 20 | Historical velocity (average story points per sprint from last 3 sprints) |
| 21 | Capacity buffer: reserve 15-20% for unexpected work, bugs, and tech debt |
| 22 | Calculate available capacity in story points or ideal hours |
| 23 | |
| 24 | **Review and select stories**: |
| 25 | Pull from the prioritized backlog (highest priority first) |
| 26 | Verify each story meets the Definition of Ready (clear AC, estimated, no blockers) |
| 27 | Flag stories that need refinement before committing |
| 28 | Stop adding stories when capacity is reached |
| 29 | |
| 30 | **Map dependencies**: |
| 31 | Identify stories that depend on other stories or external teams |
| 32 | Sequence dependent stories appropriately |
| 33 | Flag external dependencies and owners |
| 34 | Identify the critical path |
| 35 | |
| 36 | **Identify risks and mitigations**: |
| 37 | Stories with high uncertainty or complexity |
| 38 | External dependencies that could slip |
| 39 | Knowledge concentration (only one person can do it) |
| 40 | Suggest mitigations for each risk |
| 41 | |
| 42 | **Create the sprint plan summary**: |
| 43 | |
| 44 | |
| 45 | Sprint Goal: [One sentence describing what success looks like] |
| 46 | Duration: [2 weeks / 1 week / etc.] |
| 47 | Team Capacity: [X story points] |
| 48 | Committed Stories: [Y story points across Z stories] |
| 49 | Buffer: [remaining capacity] |
| 50 | |
| 51 | Stories: |
| 52 | 1. [Story title] — [points] — [owner] — [dependencies] |
| 53 | ... |
| 54 | |
| 55 | Risks: |
| 56 | - [Risk] → [Mitigation] |
| 57 | |
| 58 | |
| 59 | **Define the sprint goal**: A single, clear sentence that captures the sprint's primary value delivery. |
| 60 | |
| 61 | Think step by step. Save as markdown. |
| 62 | |
| 63 | |
| 64 | |
| 65 | ### Further Reading |
| 66 | |
| 67 | [Product Owner vs Product Manager: What's the difference?] |
| 68 |